Guide · Pricing and CAS

TINA and CAS Thresholds After the FY2026 NDAA: What Changed for Contractors

For DoD prime contracts entered into after June 30, 2026, certified cost or pricing data is required only above $10 million, up from $2.5 million. CAS applies to negotiated contracts above $35 million instead of $2.5 million, and full coverage starts at $100 million, government-wide from October 1, 2026.

  • 12 years inside DCAA
  • 100+ DoD contractors audited
  • CPA led
  • QuickBooks, Costpoint, SAP & NetSuite
  • Remote, nationwide
Alexander Mungov, CPA, former DCAA Supervisory Auditor
Alexander Mungov, CPA
Former DCAA Supervisory Auditor · Updated September 10, 2026

What Congress actually changed

The FY2026 National Defense Authorization Act (Public Law 119-60, enacted as S. 1071) was signed on December 18, 2025. Section 1804(c) amended 10 U.S.C. 3702, which decides when you must submit and certify cost or pricing data. Section 1806 amended 41 U.S.C. 1502, the Cost Accounting Standards statute, and directed a higher full coverage threshold.

The two changes run on different tracks. The certified data change is in Title 10, so it applies to defense buying, and it took effect on its own terms for contracts entered into after June 30, 2026. The CAS change is in Title 41, so it’s government-wide, but the figures that trigger full coverage and Disclosure Statements live in the CAS Board’s rules at 48 CFR Part 9903. The Board rewrote those in a final rule published September 1, 2026 (91 FR 56056), effective October 1, 2026. DoD moved first, with a July 30, 2026 class deviation that already applies $100 million to business units holding only DoD contracts.

Is TINA now the “Truthful Cost or Pricing Data Act”?

You’ll see the FY2026 changes described that way, but the NDAA didn’t rename anything. Title 41 has used “Truthful Cost or Pricing Data” as its chapter heading since the 2011 recodification, and the FY2021 NDAA moved the defense version into Title 10, chapter 271, “Truthful Cost or Pricing Data (Truth in Negotiations).” Most practitioners still say TINA. The certificate and the defective pricing remedy work the way they always have. Only the dollar figures moved.

Before and after

The thresholds, side by side

Statutory figures are adjusted for inflation every five years under 41 U.S.C. 1908, which is why the FAR showed $2.5 million while the statute said $2 million. The next scheduled adjustment is October 1, 2030.

Certified cost or pricing data, DoD prime contracts

Before: above $2.5 million. After: above $10 million for prime contracts entered into after June 30, 2026. Older contracts keep $2.5 million unless the contract says otherwise. Source: 10 U.S.C. 3702(a)(1); DFARS 215.403-3(a), Class Deviation 2026-O0048, Rev. 1.

Modifications to DoD prime contracts

DoD applies the same threshold as the contract being modified. A change to a 2024 contract still triggers at $2.5 million. A change to a contract awarded in August 2026 triggers at $10 million.

DoD subcontracts

Before: $2.5 million. After: $10 million when the prime contract was entered into after June 30, 2026, and $2.5 million under older primes. The prime contract’s date controls. Certified data flows down only when the prime and every higher tier were required to submit it.

Modifications to DoD subcontracts

Unchanged at $2.5 million. Section 1804 didn’t amend the subcontract modification paragraph, and DoD’s deviation keeps the old figure.

Civilian agency contracts

Unchanged at $2.5 million. The civilian statute, 41 U.S.C. 3502, was not amended.

CAS applicability, contract by contract

Before: negotiated contracts above $2.5 million, tied to the TINA figure, plus the $7.5 million “trigger contract” rule. After: above $35 million, decoupled from TINA, with no trigger rule. Source: 41 U.S.C. 1502(b)(1)(B); 48 CFR 9903.201-1(b)(2).

Full CAS coverage and Disclosure Statements

Before: a single CAS-covered award of $50 million, or $50 million in net CAS-covered awards in the prior cost accounting period. After: $100 million on both tests. Source: 48 CFR 9903.201-2 and 9903.202-1; DFARS 230.201-70, Class Deviation 2026-O0006, Rev. 1.

Commercial, fixed-price and price-set-by-law portions

These CAS exemptions now apply to the portion of a contract, which matters on hybrids that mix firm-fixed-price and cost-type line items. Source: 41 U.S.C. 1502(b)(1)(C).

Indefinite delivery contracts

New: multiple-award IDCs are tested for CAS at each task or delivery order. Single-award IDCs are tested once, at award, against the ceiling. Source: 48 CFR 9903.201-1(c).

Certified data

How the $10 million threshold works in practice

The test is when the prime contract is entered into, meaning the award date. A proposal submitted in May 2026 for a contract awarded in August 2026 falls under the new threshold. A contract awarded in March 2026 doesn’t, and neither do its later modifications.

  • Who it covers. The Title 10 pricing chapter covers DoD, NASA and the Coast Guard (10 U.S.C. 3063). DoD implemented it by class deviation. If you sell to NASA or the Coast Guard, confirm that agency’s implementation before relying on $10 million.
  • Civilian agencies. No change. GSA, VA and the rest of the civilian side still use $2.5 million.
  • Nontraditional defense contractors. Section 1826 exempts them (10 U.S.C. 3014) from 10 U.S.C. 3702 altogether, along with FAR Part 31 and the six DFARS business systems clauses and 252.242-7005, unless the head of the contracting activity waives it in writing.

CAS

Where CAS stands: statute, DoD deviation, CAS Board rule

Be precise about which layer you’re relying on. A contract’s CAS status comes from the regulation and the clauses in the contract, not the statute alone.

December 18, 2025: the statute changes

Section 1806 set the applicability threshold at $35 million, deleted the $7.5 million trigger test, extended the exemptions to portions of contracts, and required a $100 million full coverage threshold within 180 days.

July 30, 2026: DoD’s Part 230 deviation

Class Deviation 2026-O0006, Rev. 1 applies $100 million for full coverage and Disclosure Statements to business units with only DoD contracts, and uses the statutory $35 million at the contract level. Units with mixed DoD and civilian work stayed on the FAR figures until the Board acted.

October 1, 2026: the CAS Board rule takes effect

The rule amends 48 CFR 9903 government-wide: the $35 million exemption, $100 million for full coverage and Disclosure Statements, the IDC rules, and a transition path from full to modified coverage.

Still pending

The FAR Part 30 text and 52.230 clauses outside DoD still need conforming, and the Board has opened a separate case on the Section 1806 changes to contract price adjustments under 41 U.S.C. 1503.

The CAS Board estimated the higher applicability threshold would cut the number of CAS-covered business segments by about 60 percent while keeping over 90 percent of the dollars now covered.

Who benefits

Who gets the most out of the new thresholds

01

Firms that outgrew small business status

Small businesses were always exempt from CAS. The pain started when a company lost its size status and won a negotiated award above $7.5 million, which pulled later awards above $2.5 million under CAS too. Now it takes a contract above $35 million, and below $100 million modified coverage is generally available.

02

New entrants and nontraditionals

A sole-source DoD award between $2.5 million and $10 million no longer needs a certified proposal. Nontraditional status depends on not having performed a full-coverage CAS contract for DoD in the year before the solicitation, and at $100 million fewer firms will trip that test.

03

Subcontractors

Under new primes, certified data flows down only above $10 million and CAS only above $35 million. But subcontract modifications still trigger at $2.5 million, and subcontracts under older primes keep the old figure.

04

Mid-tier contractors under full coverage

A business unit below the $100 million tests can move full-coverage contracts to modified coverage at the start of its next full cost accounting period beginning on or after October 1, 2026, if it has no unresolved CAS noncompliances.

Still in force

What does not go away

The certificate goes away for many actions. The contracting officer’s duty to reach a fair and reasonable price stays, and so do the rules for cost-type work.

Data other than certified cost or pricing data

The contracting officer must still get whatever data is needed to determine a fair and reasonable price (10 U.S.C. 3705; FAR 15.403-1), at a minimum prices at which the same or similar items have sold. Prices the government paid before can’t be the sole basis, and an offeror that won’t make a good faith effort to provide requested data can be found ineligible for award.

Certified data below the threshold, in rare cases

The head of the procuring activity can still require it when needed to evaluate price reasonableness, with a written justification and no delegation (10 U.S.C. 3704).

DCAA proposal audits

DCAA still audits proposals. DoD’s pricing guidance (PGI 215.406, revised with the July 2026 deviation) points contracting officers to DCAA audit assistance for fixed-price proposals over $10 million and cost-type proposals over $100 million. Below that, the buying office usually does its own analysis, but it can still bring in help for an unfamiliar offeror.

Cost-type contract rules

FAR Part 31 allowability, the Allowable Cost and Payment clause, incurred cost submissions and accounting system adequacy were never tied to the TINA threshold and still apply. The exception is a nontraditional defense contractor covered by Section 1826, which is also exempt from the business systems clauses unless the exemption is waived.

Contracts you already hold

CAS clauses, certificates and defective pricing clauses in existing contracts stay in force, and defective pricing reviews of those contracts can still happen.

Modified coverage

Modified coverage is still CAS: standards 401, 402, 405 and 406, and a change in practice still goes through the cost impact process.

Evaluation

What the auditor actually looks at

Here’s how a proposal under the new threshold still gets evaluated, based on the public regulations and how these reviews generally run. The contracting officer starts with price analysis, and with adequate price competition that may be the end of it. The FAR’s order of preference is no additional data, then price-related data, then cost data only as needed. On sole-source work there’s usually nothing to compare against, so expect a cost data request anyway.

On a DoD fixed-price action under $10 million, the reviewer is more likely the buying office’s price analyst than a DCAA auditor. Either way, the review looks a lot like a certified proposal audit without the certificate. Expect them to trace each element back to something real:

  • Labor hours. Your basis of estimate: historical actuals from similar jobs, an engineering estimate with a named estimator and method, or parametric factors you can support. “Engineering judgment” with nothing underneath gets questioned.
  • Labor rates. Traced to payroll, with escalation you can explain.
  • Indirect rates. Tied to a forward pricing rate agreement or proposal, your provisional billing rates, or your latest actuals, with a clear reason for any difference.
  • Material and subcontracts. Quotes, evidence of competition, and your own price or cost analysis of significant subcontracts. The prime’s evaluation of its subs gets reviewed like the rest of the proposal.
  • Commercial pricing claims. Sales history verified to source documents, and the discounts you normally give.
  • Consistency. Whether you estimate the way you accumulate and report actual cost. If you’re CAS covered, even under modified coverage, that’s a CAS 401 question.

On cost-reimbursement competitions, evaluators also run cost realism. They adjust your proposed cost to a probable cost and use that number to evaluate best value. An unrealistically low labor or indirect rate gets adjusted upward, and it can hurt your risk rating along the way.

What changes below the threshold is the aftermath. There’s no certificate of current cost or pricing data, no cutoff date sweep and no post-award defective pricing audit on that contract. The data still has to be accurate. Misstatements in uncertified data carry their own legal exposure, and if that question comes up, we work alongside your counsel.

Next steps

What to do now

Inventory open proposals and subcontracts

List every pending proposal, open prime contract and subcontract, with the prime contract’s award date beside it. That date decides whether $2.5 million or $10 million applies, for you and for anything you flow down.

Update flowdown clauses and subcontract templates

Subcontracts under new primes need the $10 million figure, those under older primes keep $2.5 million, subcontract modifications stay at $2.5 million, and CAS clauses belong only on subcontracts above $35 million that aren’t otherwise exempt.

Decide whether to keep a Disclosure Statement

Below the $100 million tests, new awards no longer require one, and existing full-coverage contracts may move to modified coverage. The CAS Board treats practice changes tied to that transition as unilateral changes subject to price adjustment, so plan the timing and cost impact first.

Watch the FAR overhaul and CAS Board rulemaking

Track the Part 15 and Part 30 texts, DoD’s deviations, the Board’s contract price adjustment case, and how DoD applies Section 812, which rewrote the statutory wording of the adequate price competition exception in 10 U.S.C. 3703.

Regulatory status

A note on the FAR overhaul and DoD deviations

All of this lands in the middle of the Revolutionary FAR Overhaul launched by Executive Order 14275 on April 15, 2025. Rewritten FAR parts are published as model deviation text on acquisition.gov, and agencies adopt them by class deviation until the FAR Council’s formal rules are final.

For DoD, three deviations matter here: 2026-O0048, Rev. 1 (Part 15 and DFARS 215, July 22, 2026), with the $10 million threshold and the nontraditional exemption; 2026-O0006, Rev. 1 (Part 30 and DFARS 230, July 30, 2026), with the $100 million CAS thresholds; and 2026-O0032, Rev. 1 (Part 31 and DFARS 231, August 4, 2026), the cost principles. DoD lists them on its FAR overhaul class deviation index.

Paragraph numbers have moved too: the threshold at FAR 15.403-4 sits at 15.403-3 in the overhaul text, still at $2.5 million for civilian buys. Because the FAR is mid-rewrite and DoD deviations apply in place of the codified text, we check the current text of every part we cite on every engagement.

Questions

Frequently asked

Does the $10 million threshold apply to contracts we already have?

No. It applies to DoD prime contracts entered into after June 30, 2026. Older contracts keep the $2.5 million threshold unless the contract says otherwise, and DoD applies the same threshold to a modification as to the contract being modified.

Do civilian agencies use the $10 million threshold?

No. The civilian statute, 41 U.S.C. 3502, wasn’t amended, so civilian agencies still require certified cost or pricing data above $2.5 million. The Title 10 change also reaches NASA and Coast Guard buying, so check how those agencies have implemented it.

If our proposal is under $10 million, can the contracting officer still ask for cost data?

Yes. The contracting officer must obtain data other than certified cost or pricing data to the extent needed to determine a fair and reasonable price, and on sole-source work that usually means cost data. Refusing a reasonable request can make you ineligible for award.

When does the $35 million CAS threshold take effect?

The statute changed on December 18, 2025. DoD applied it to DoD-only business units by class deviation on July 30, 2026, and the CAS Board’s final rule makes it effective government-wide on October 1, 2026. FAR clause updates outside DoD are still pending.

We have a Disclosure Statement on file. Can we stop maintaining it?

Possibly. After October 1, 2026 a Disclosure Statement is required only for business units that meet the $100 million full coverage tests. Existing full-coverage contracts can move to modified coverage if you have no unresolved CAS noncompliances, but related practice changes are treated as unilateral and can carry a cost impact.

Does any of this change our cost-type contracts?

Mostly no. FAR Part 31 allowability, incurred cost submissions, accounting system adequacy and cost realism in competitions don’t depend on the TINA or CAS thresholds. The main exception is a nontraditional defense contractor covered by Section 1826, unless the exemption is waived.

More

Related services

Truthful Cost or Pricing Data support

Certified proposals, sweeps and defective pricing exposure, on contracts under the old and new thresholds.

Learn more →

CAS Disclosure Statements

Form CASB DS-1 preparation, the move from full to modified coverage, and cost impact analysis.

Learn more →

Contract pricing & proposal support

Cost volumes and bases of estimate that hold up when the contracting officer asks for data other than certified.

Learn more →

Forward pricing rates (FPRP & FPRA)

Forward pricing rate proposals and agreements so your indirect rates stop being the argument in every negotiation.

Learn more →

Alexander Mungov, CPA, former DCAA Supervisory Auditor

Alexander Mungov, CPA

Founder and principal, M2 CPA

Alexander Mungov spent twelve years at the Defense Contract Audit Agency, in the Denver, European and Afghanistan branch offices, finishing as a Supervisory Auditor leading a team of six. He then built and ran the FAR, DFARS and CAS compliance program inside a defense technology company, as the primary liaison with DCAA and DCMA.

He founded M2 CPA to give small and mid-size contractors the compliance support that large primes take for granted. More about Alex.

Not sure which threshold applies to you?

Send us your open proposals and largest contracts. We’ll tell you which ones still need certified data, where CAS applies, and whether your Disclosure Statement still earns its keep.